CARRIAGE BARN - Construction Pictures


December 2002 - Excavation work completed

March 25, 2003 - Construction of building begins.

March 25, 2003 - Poles for building

March 26, 2003 - Framing has begun.

March 28, 2003 - Building is at full length.

April 16, 2003 - Trusses have been attached.

April 17, 2003 - Framework is completed.

April 18th, 2003 - Installation of the brown aluminum roof was begun, but was halted by a rainstorm.

April 21, 2003 - The roof is completed and one of the cupolas was installed.

April 23, 2003 - In winter-like conditions, including snow, most of the aluminum siding was installed.

April 25, 2003 - All of the aluminum work is complete.

April 30, 2003

  Rough-sawn Hemlock was attached to the front of the barn and the second cupola was attached. The carriage barn is nearing completion.

May 5, 2003

 The carriage barn is complete with the exception of the last two overhead doors which will be installed a few weeks.

June 6th, 2003

The Carriage Barn is complete!!!

www.dougschmittantiques.com